Data Center Application Can be Denied Right Now
Holmdel Township Committee and Planning Board
The Planning Board can stop the data center application dead in its tracks right now by telling the applicants it lacks jurisdiction to hear it.
In its October 2, 2026, letter to the Holmdel Planning Board, Van Cleef Engineering states that Somerset’s proposed data center does not conform to the 2012 Redevelopment Plan.
The Redevelopment Plan permits a data center only within the general footprint of Bell Works’ existing maintenance building. The proposed 40-megawatt facility exceeds that boundary, with its main building extending 30–38 feet beyond two walls.
Moreover, the Redevelopment Plan explicitly defines a data center to include generators, transformers, and switchgear. The entire proposed facility, including the generator yard and the other equipment, occupies approximately 34% more area than the existing footprint and therefore is not a permitted use under the Plan.
The Planning Board cannot proceed with substantive site-plan review of an application that exceeds its jurisdiction. Therefore, we urge the Planning Board to notify the applicant immediately that it lacks jurisdiction to approve the application as submitted.
The Mayor, or his designee, and Committee Member Gary Vanderham serve on the Planning Board.
Ask the Township Committee and the Planning Board to protect Holmdel and say NO to the data center application.
Please sign our petition, then share it with your family, friends, and neighbors.
SHIELD - Stop Holmdel Industrial Energy Load Data-center
###
Follow us on Facebook: https://www.facebook.com/profile.php?id=61593331944176
Link to our Donate page: https://shieldholmdel.wixsite.com/home/donate
Sign up for updates: https://forms.gle/Lc8zkmb9FFPSrXGB7
Website: https://shieldholmdel.wixsite.com/home
Contact us at: info@shieldholmdel.org
Sponsored by
To:
Holmdel Township Committee and Planning Board
From:
[Your Name]
In its October 2, 2026, letter to the Holmdel Planning Board, Van Cleef Engineering states that Somerset’s proposed data center does not conform to the 2012 Redevelopment Plan.
The Redevelopment Plan permits a data center only within the general footprint of Bell Works’ existing maintenance building. The proposed 40-megawatt facility exceeds that boundary, with its main building extending 30–38 feet beyond two walls.
Moreover, the Redevelopment Plan explicitly defines a data center to include generators, transformers, and switchgear. The entire proposed facility, including the generator yard and the other equipment, occupies approximately 34% more area than the existing footprint and therefore is not a permitted use under the Plan.
This is a use issue—not merely a bulk variance or design waiver.
The Planning Board cannot proceed with substantive site-plan review of an application that exceeds its jurisdiction. Therefore, we urge the Board to notify the applicant immediately that it lacks jurisdiction to approve the application as submitted.
Thank you.